Vlad Alexandru Stacescu

Senior Site Manager · Civil Engineer

15 years delivering infrastructure, energy, industrial and building projects in Australia, the UK, Romania, Slovakia and Turkmenistan.

15
years
5
countries
500+
workers coordinated on one site
up to €650m
project value

Projects

InfrastructureJun 2025 – Nov 2025

River Torrens to Darlington (T2D)

Adelaide, SA, Australia · A$7bn motorway

Senior Site Manager
Bouygues Construction Australia

My scope: Surface works package for 2 of the 4 tunnel portals, A$40m.

  • CFA piles and diaphragm walls
  • Organised subcontractors, vendors and third parties; controlled cost and programme
  • Wrote method statements
EnergyFeb 2025 – Jun 2025

Goorambat East Solar Farm 250 MW

Benalla, VIC, Australia · A$220m

Senior Site Manager
Bouygues Construction Australia

My scope: All works on half of the site, A$60m, 300+ workers.

  • Piling, DC and MV cabling, trackers (ATI and Nextracker) and PV modules
  • Procurement, logistics, planning, methods and construction
  • Managed work packages and subcontractors
EnergyMar 2024 – Feb 2025

Culcairn Solar Farm 440 MW

Culcairn, NSW, Australia · A$420m

Senior Site Manager
Bouygues Construction Australia

My scope: Mechanical package: 7,500 Nextracker trackers, A$60m, 200+ workers.

  • Built the procedures used to track cost and programme
  • Method statements and training
  • Quality and HSE compliance
IndustrialMar 2023 – Oct 2023

Nokian Tyres production plant

Oradea, Romania · €650m

Senior Site Manager
ACE Project ManagementClient: Nokian Tyres

My scope: Enabling works on a 500,000 m² site with up to 4 major contractors and 500+ workers.

  • 300,000 m³ of earthworks, 3,000 m² retention pond
  • 20,000 m² of car parks, 2 km of temporary roads
  • Design and construction coordination to hit milestones
BuildingsJun 2022 – Feb 2023

Silk District mixed-use development

Iași, Romania · €250m

Senior Site Manager
Prime Kapital

My scope: One office building, 2 basements + 8 storeys, €40m.

  • Built and led a team of 5 construction managers
  • Coordinated up to 8 labour-only contractors (200 workers)
  • Value engineering, QA/QC and HSE plans
IndustrialSep 2021 – Jun 2022

Lidl distribution warehouse

Craiova, Romania · €65m

Senior Site Manager
ACE Project ManagementClient: Lidl

My scope: Supervised the main contractor from site set-up to structure.

  • Piling, earthworks, roads, cast in situ and precast structure
  • Programme, quality, cost and safety control
  • Design coordination and approvals
BuildingsDec 2020 – Aug 2021

Sugar House Island

London, UK · £160m

Senior Site Manager
Vastint

My scope: Internal trades and MEP for a 120-apartment residential building, £60m.

  • Coordinated 6 contractors and 200+ workers
  • Bespoke programmes and workflows
  • Snagging and handover to the client
BuildingsSep 2019 – Sep 2020

Turkmenbashy Bank headquarters

Ashgabat, Turkmenistan · $30m

Senior Site Manager
Bouygues Construction

My scope: Concrete frame, roads and underground utilities for a 12-storey office building.

  • Led a multicultural team; packages on time and on budget
  • Procurement and cost control, design coordination
  • Testing, commissioning and O&M manuals
InfrastructureAug 2017 – Sep 2019

Jaguar Land Rover car plant

Nitra, Slovakia · €1.5bn (infrastructure contract €51m)

Site Manager
Colas Slovakia

My scope: External networks and landscaping, €51m contract.

  • 10 km fire main (ductile iron DN150–DN400), 15 km rainwater, 7 km sewer
  • Roads and 200,000 m² of landscaping
  • Commissioning, snagging and handover

Earlier roles

  1. Feb 2016 – Aug 2017

    Construction Supervisor

    EnelSlovenské elektrárne

    Mochovce Nuclear Power Plant Units 3&4, Slovakia (€4bn)

    Civil and infrastructure works for the Conventional Island.

  2. Aug 2015 – Jan 2016

    Site Manager

    Colas Slovakia

    R2 bypass Ruskovce – Pravotice, 10 km (€88m)

    Earthworks and rainwater drainage.

  3. Feb 2013 – Apr 2015

    Site Manager

    Colas Slovakia

    Mochovce Nuclear Power Plant Units 3&4 (contract €250m)

    Structural strengthening, painting and doors.

  4. Sep 2010 – Feb 2013

    Site Engineer

    Romstrade

    DN6 national road rehabilitation, 45 km, Romania (€60m)

    Earthworks, asphalt, drainage, bridges.